Algunos de ustedes habrán tenido la mala suerte de luchar con las referencias circulares en Project. En una consulta de los foros de Microsoft, Sapna Shukla nos explica como eliminarlas. El resumen es:
- La causa principal son las relaciones en las tareas sumarias.
- Con lo cual la solución pasa por evitar ese tipo de relaciones
Transcribo cómo nos propone eliminarlas:
The most identifiable cause of circular relationships is links on summary lines. Turn off automatic calculation for a while from File - Options - Schedule -Calculation Tab, and then go to View - > Outline -> All sub tasks to expand the file. Now delete all summary links from predecessors n successors to elimniate any cause.
Yet another quick way is create a Custom field and copy all Predecessors into it and delete all values from Predecessor Column; now copy values from this custom field and paste as it is in Predecessor column now it should prompt on pasting which all links are errorneous and leading to Circular dependencies, you can delete them.
Sapna S
1 comentarios:
Launch the project in your preferred development environment. Locate the section where references are managed. 6800k Vs 6700k This may be in the project settings or properties.
Publicar un comentario